- Data
- Money
- Product
- Regulation & influence
- 1Data
RFQ issued
Purchasing sends a request for quotation with drawings, volumes, and target price years before SOP.
- 2Money
Supplier quotes
Tier 1s quote piece price, tooling cost, and engineering cost, often with annual price-down commitments.
- 3Money
Nomination
A sourcing committee picks the winner and issues a nomination letter for the life of the program.
- 4Product
Sub-tier sourcing
The Tier 1 sources castings, electronics, and small parts from its own Tier 2 and Tier 3 suppliers.
- 5Product
Material secured
Steel, aluminum, and resin contracts are set, sometimes through automaker resale programs that pool volume.
- 6Data
APQP and tooling
The supplier builds tooling and works through APQP milestones with the automaker's supplier quality engineers.
- 7Regulation & influence
PPAP approval
Production samples and documentation pass PPAP, proving the process makes good parts at rate.
- 8Product
Just-in-time delivery
Logistics providers run milk runs and sequencing centers so parts arrive in the order cars come down the line.
- 9Product
Installed on the line
The part is fitted at its station within takt time; defects trigger containment and chargebacks to the supplier.