- 1Design and process planningSupplier
- 2Production trial runSupplier
- 3Measurements and capability
- 4PSW submittedSupplier
- 5ApprovalOEM
Key terms, explained
- APQP
- Advanced Product Quality Planning, the phased plan from design to launch.
- PPAP
- Production Part Approval Process: the evidence package showing parts from production tooling meet requirements.
- Part Submission Warrant (PSW)
- The signed summary that the supplier submits to get a part approved.
- Submission level
- Levels 1 to 5 define how much evidence is sent; level 3 is the usual default.
- Control plan and PFMEA
- Documents showing how process risks are analyzed and controlled.
- Process capability
- Statistical proof (Cpk) that a process is stable; targets such as 1.33 or 1.67 are common.
- Run at rate
- A trial showing the line can make parts at the required speed and quality.
- PPM target
- Allowed defective parts per million delivered.
- 8D and containment
- Structured problem solving and controlled shipping (CS1 or CS2) after defects.
- Change notification
- No process, site, or material change without prior customer approval.
- IATF 16949 certification
- The automotive quality management standard most OEMs require.
- Customer-specific requirements
- Each OEM's additions to the common standards.
How the money works
Quality failures cost money: OEMs charge back sorting, line downtime, containment, and warranty costs, and suppliers on controlled shipping pay for third-party inspection. Good performance affects eligibility for new business.
How it differs by country
The AIAG PPAP manual (4th edition) and APQP are the reference for GM, Ford, and Stellantis, with each OEM's customer-specific requirements.
German OEMs use VDA Volume 2 (Production Process and Product Approval, PPF) and VDA 6.3 process audits, managed by VDA QMC.
Japanese OEMs apply their own supplier quality manuals alongside IATF 16949, with heavy emphasis on on-site audits.
Chinese OEMs generally require IATF 16949 plus their own audits; many suppliers hold certification to serve both domestic and foreign brands.
ACMA and OEMs promote IATF 16949 and zero-defect programs among Indian suppliers.
In detail
- ↓ flows down PPAPTier 2 and 3
When defects escape, escalation is fast and costly.
- 1Defect at OEM plant
- 2Containment and sorting
- 38D root cause
- 4Controlled shipping CS1
- 5CS2 third-party, new business hold
North American and German approval systems cover the same ground with different documents.[1][3]
- 118 elements
- 2PSW
- 3Submission levels 1 to 5
- 1Production process approval
- 2Cover sheet and reports
- 3VDA 6.3 process audit
Sources
- 1Production Part Approval Process (PPAP) manual , Automotive Industry Action Group
- 2IATF 16949 global oversight , International Automotive Task Force
- 3VDA Quality Management Center , VDA QMC