The quality rules a supplier must meet before and during production, including advanced product quality planning, the Production Part Approval Process (PPAP) or VDA equivalent, certification, defect targets, and what happens when bad parts reach the customer.

.md
Between
Tier 1 suppliersOEMs (automakers)
Typical term For the life of the supply relationship; PPAP is repeated for new parts and changes.
The relationship it governs →
01

Key terms, explained

APQP
Advanced Product Quality Planning, the phased plan from design to launch.
PPAP
Production Part Approval Process: the evidence package showing parts from production tooling meet requirements.
Part Submission Warrant (PSW)
The signed summary that the supplier submits to get a part approved.
Submission level
Levels 1 to 5 define how much evidence is sent; level 3 is the usual default.
Control plan and PFMEA
Documents showing how process risks are analyzed and controlled.
Process capability
Statistical proof (Cpk) that a process is stable; targets such as 1.33 or 1.67 are common.
Run at rate
A trial showing the line can make parts at the required speed and quality.
PPM target
Allowed defective parts per million delivered.
8D and containment
Structured problem solving and controlled shipping (CS1 or CS2) after defects.
Change notification
No process, site, or material change without prior customer approval.
IATF 16949 certification
The automotive quality management standard most OEMs require.
Customer-specific requirements
Each OEM's additions to the common standards.
02

How the money works

Quality failures cost money: OEMs charge back sorting, line downtime, containment, and warranty costs, and suppliers on controlled shipping pay for third-party inspection. Good performance affects eligibility for new business.

03

How it differs by country

United States

The AIAG PPAP manual (4th edition) and APQP are the reference for GM, Ford, and Stellantis, with each OEM's customer-specific requirements.

Germany

German OEMs use VDA Volume 2 (Production Process and Product Approval, PPF) and VDA 6.3 process audits, managed by VDA QMC.

Japan

Japanese OEMs apply their own supplier quality manuals alongside IATF 16949, with heavy emphasis on on-site audits.

China

Chinese OEMs generally require IATF 16949 plus their own audits; many suppliers hold certification to serve both domestic and foreign brands.

India

ACMA and OEMs promote IATF 16949 and zero-defect programs among Indian suppliers.

04

In detail

A part is not approved for production until PPAP is accepted.[1]

Verified Link
  1. 1
    Design and process planning
    Supplier
  2. 2
    Production trial run
    Supplier
  3. 3
    Measurements and capability
  4. 4
    PSW submitted
    Supplier
  5. 5
    Approval
    OEM
The PPAP path to approval.

When defects escape, escalation is fast and costly.

Consensus Link
  1. 1Defect at OEM plant
  2. 2Containment and sorting
  3. 38D root cause
  4. 4Controlled shipping CS1
  5. 5CS2 third-party, new business hold
Quality escalation after a defect.

North American and German approval systems cover the same ground with different documents.[1][3]

Consensus Link
AIAG PPAP
  • 118 elements
  • 2PSW
  • 3Submission levels 1 to 5
VDA PPF (Volume 2)
  • 1Production process approval
  • 2Cover sheet and reports
  • 3VDA 6.3 process audit
AIAG versus VDA approval.
Footnotes

Sources

  1. 1Production Part Approval Process (PPAP) manual , Automotive Industry Action Group
  2. 2IATF 16949 global oversight , International Automotive Task Force
  3. 3VDA Quality Management Center , VDA QMC
Before you go

Did you find what you came here for?